Metra Nirou, as a small member of the large family of electricity industry, has played an effective and constructive role in the country’s engineering activities.

contact us

Equipment supply project and full implementation of 33 kV line of Charam Phosphate Plant and South Maghar Lime Mine

Client: Iran Mines Development and Renovation Organization

Consultant: No Andishan Design Company

Year of work: 1401

Equipment supply project and complete implementation of completion of communications of 63 kV lines of Vavan, Baharestan and Mehr Mianabad housing

Client: Tehran Regional Electricity Company

Consultant: Mashanir Company

Year of work: 1401

Project for repairing and eliminating the defects of the 63 kV Ameri-Amin Al-Ashrafi line

Client: Tehran Regional Electricity Company

Consultant: Quds Niroo Company

Year of work: 1400

The project of transporting lattice towers and fittings and installing towers and performing wiring operations and constructing the foundation of metal lattice towers at the entrance and exit of 132 kV Mahabad Sardasht line at Khalifan post

Client: Azerbaijan Regional Electricity Company

Consultant: Azerbaijan Power Consulting Engineering Company

Year of work: 1400

Project of rerouting 230 kV lines of Gilan Speed ​​Road power plant and Gilan Lushan power plant in Shamam Rudbar mine

Client: Gilan Regional Electricity Company

Consultant: Mashanir Company

Year of work: 1400

Equipment procurement project and implementation of entry and exit of Ahar Sabalan 230 kV line in the new 230 kV substation of Meshkinshahr

Client: Azerbaijan Regional Electricity Company

Consultant: Quds Niroo Company

Year of work: 1400

Project for preparation and complete implementation of 33 kV power transmission line to Jam city

Client: Afrineh Tous Company

Consultant: Pars Payab Company

Year of work 1399

Power supply project for pump houses No. 1 and 2 of Goreh-Jask crude oil transmission lines project

Client: Petroleum Engineering and Development Company – Abadrahan Pars Company

Consultant: Quds Niroo Company

Year of work: 1399

Completion of 63 kV communication project of 230 Baharestan (Golestan) post, second phase

Client: Tehran Regional Electricity Company

Consultant: Saturation Power Company

Year of work: 1398

Executive operation project and elimination of defects and deficits of 63 kV Varamin line towers

Client: Tehran Regional Electricity Company

Consultant: Azerbaijan Power Consulting Engineering Company

Year of work: 1398

Project of purchasing equipment and carrying out executive operations of 230 kV communication lines of Golestan post through entering and leaving the 230 kV Parand-Firooz Bahram line

Client: Tehran Regional Electricity Company

Consultant: Mashanir Company

Year of work: 2017

Project for purchasing equipment and carrying out executive operations of the 63 kV line of Mehr Mianabad housing

Client: Tehran Regional Electricity Company

Consultant: Mashanir Company

Year of work: 2017

Procurement of equipment and complete implementation of the foundation and tower of the 230 kV Khalkhal line

Client: Azerbaijan Regional Electricity Company

Year of work: 2017

Procurement of equipment and complete implementation of the foundation, tower and wiring of the 63 kV Varamin line

Client: Tehran Regional Electricity Company

Year of work: 2017

Replacement of wires and wiring part of the 230 kV single line Lushan_Qazvin

Client: Zanjan Regional Electricity Company

Year of work: 1394

Procurement of equipment and construction of foundation, rigging and wiring of 63 kV Poldakhtar 2 line and slum

Client: Bakhtar Regional Electricity Company

Year of work: 1392

Procurement of equipment and construction of foundations, masts and wiring of 230 and 400 lines around the 400 kV Mehr and 400 kV fig substations

Client: Bakhtar Regional Electricity Company

Year of work: 1392

Procurement of equipment and construction of foundation, mast and wiring of 63 kV line of Ashtian Industrial City

Client: Bakhtar Regional Electricity Company

Year of work: 1391

Preparation and execution of rigging and wiring of 63 kV four-circuit tight technical and Afrineh line at 230 Poldakhtar substation

Client: Bakhtar Regional Electricity Company

Year of work: 1390

Preparation and implementation of foundation, rig and wiring of 400 kV end line – Tabriz

Client: Azerbaijan Regional Electricity Company

Year of work: 2009

Preparation and implementation of the foundation of 63 kV four-circuit line Malayer – Shushab

Client: Bakhtar Regional Electricity Company

Year of work: 2008

Preparation and implementation of the foundation of 63 kV double circuit line Shushab – Tuyserkan

Client: Bakhtar Regional Electricity Company

Year of work: 2008

Preparation and implementation of 63 kV line foundation for Harris substation

Client: Azerbaijan Regional Electricity Company

Year of work: 2007

Project for construction of foundation, mast and wiring of 400 kV line Qom – Golpayegan

Client: Esco Company

Susangard 230 kV line wiring project – northwest of Ahvaz

Client: Gravity Company

Construction project of foundation, mast and wiring of 63 kV line of Ziaran post – Taleghan city

Client: Tehran Dekel Company

Construction project of the 400 kV line of Wardavard Tehran – Changli Park, Tehran

Client: Tehran Dekel Company

Construction of the foundation of 63 kV line Chavar – Ilam Petrochemical Refinery

Client: Octad Company

Construction of 63 kV Shams Abad-Fashavieh line foundation

Client: Dena Energy Company

Construction of 400 kV line foundation of Shahid Rajaei power plant in Qazvin – Wardavard, Tehran

Client: Tehran Dekel Company

Project for the construction of the 230 and 63 kV line of the campus – Lar Dam

Client: Tehran Dekel Company

Dehloran post 230 kV line foundation, rig and wiring construction project – Dehloran Cement Factory

Client: Raad Energy Aria Company

Equipment supply project and full implementation of 20 kV line of Shaqez mine in Lorestan province

Client: Iran Mines Development and Renovation Organization

Consultant: No Andishan Design Company

Year of work: 1401

Equipment supply project and complete construction of 20 kV two-circuit overhead line of Ghani Abad lead and zinc mine in South Khorasan province

Client: Iran Mines Development and Renovation Organization

Consultant: Navandishan Design Company

Year of work: 1400

Executive operation project for the construction of a medium pressure network for the distribution of internal electricity at the shrimp farming site of Rudshour fishery town

Client: Agricultural Towns Company

Consultant: Moheb Niroo Shiraz Company

Year of work: 1398

Execution operation project of Wavan 20/63 kV substation communication reform

Client: Tehran Regional Electricity Company

Consultant: Mashanir Company

Year of work: 1398

Project of supply and supply of equipment and complete executive operation of construction of 20 kV line from Soltanieh distribution post and Tarom copper factory

Client: Iran Mines Development and Renovation Organization

Consultant: Navandishan Design Company

Year of work: 1397

Procurement of complete equipment and construction of 6 km 20 kV overhead line and 3 km 20 kV overhead line of Ajab Shir greenhouse complex

Client: East Azerbaijan Agricultural Jihad Organization

Year of work: 1394

Procurement of equipment and complete construction of 1 km of 20 kV overhead line and 1 ground post machine 1250 refueling of Mehrabad airline

Client: Iran Petroleum Products Distribution Company

Location: Fueling Mehrabad Airport

Year of work: 1392

Procurement of equipment and complete construction of 6 km of 20 kV line and 6 air mail machines

Employer: General Department of Roads and Transportation of Ardabil Province

Location: Ardabil province

Year of work: 1390

Procurement of equipment and complete construction of 16 km of 20 kV line and 10 50 kv air post machines

Employer: General Department of Roads and Transportation of Markazi Province

Location: Markazi-Arak axis, Rahjerd

Year of work: 1389

Procurement of equipment and complete construction of 15 km of 20 kV line and 3 1250 ka and A ground substations Mehr housing projects in Kermanshah

Client: Kermanshah Power Distribution Company

Location: Kermanshah province

Year of work: 1389

Design, preparation and implementation of Khalkhal-Asalem axis lighting system as EPC

Employer: General Department of Roads and Transportation of Ardabil Province

Location: Ardabil province

Year of work: 1389

Procurement of equipment and complete construction of 4 km of 20 kV line and 3 50 kv overhead lighting devices of Bandar Abbas-Minab axis lighting network

Employer: General Department of Roads and Transportation of Hormozgan Province

Location: Bandar Abbas – Minab axis

Year of work: 2007

Procurement of equipment and full implementation of 9.5 km of 20 kV network and low lighting and low pressure of Chah Tar livestock complex

Employer: Hormozgan Agricultural Jihad Organization

Location: Hajiabad city

Year of work: 2005

Procurement of equipment and complete implementation of 10 km of 20 kV overhead network and installation of 50 kV substation of Sarzeh Rapiter amplifier

Client: Hormozgan Telecommunication Company

Location: Rudan city

Year of work: 2005

Procurement of equipment and complete implementation of 4.5 km of 20 kV overhead network, low pressure and 2 compact substations in Mir Mahna town

Client: Kish Urban Development and Services Company

Location: Kish Island

Year of work: 2004

Procurement of equipment and complete implementation of 8 km of 20 kV overhead network and connection to Rudbar power plant

Client: Oramab Company

Location: Baznovid area of ​​Aligudarz city

Year of work: 2004

Project to buy 2300 low-consumption LED lamps, street lights and projectors

Client: Bakhtar Regional Electricity Company

Year of work: 2017

Design project, equipment supply and complete construction of street lighting system in Tehran International Exhibition

Client: Iran International Exhibitions Company 

Year of work: 1395

Design, preparation and implementation of lighting system for the neck

Employer: General Department of Roads and Transportation of Tehran Province

Location: Tehran province

Year of work: 1392

Design, preparation and implementation of Khalkhal-Asalem axis lighting system as EPC

Employer: General Department of Roads and Transportation of Ardabil Province

Location: Ardabil province

Year of work: 1390

Construction and installation of a 30-meter lighting tower for passenger parking

Client: Shahid Tondgovian Oil Refining Company, Tehran

Location: Shahid Tondgovian Oil Refinery, Tehran

Year of work: 1390

Design, preparation and implementation of Arak-Rahjerd lighting operation as EPC

Employer: General Department of Roads and Transportation of Markazi Province

Location: Markazi-Arak axis, Rahjerd

Year of work: 1389

Design and implementation of lighting network of Bandar Abbas-Minab axes as EPC

Employer: General Department of Roads and Transportation of Hormozgan Province

Location: Bandar Abbas – Minab axis

Year of work: 2007

Design, preparation and implementation of Bandar Abbas-Sirjan axis lighting network between Holy Defense and Namjoo squares as EPC

Client: Hormozgan Regional Electricity Company

Location: Bandar Abbas city

Year of work: 2004

Design, preparation and implementation of street lighting network in Nazarabad industrial town as EPC

Client: Tehran Industrial Towns Company

Location: Nazarabad Industrial Town, 25 km from Qazvin

Year of work: 2002

Design, preparation and implementation of Tabriz-Zanjan axis lighting system (Ata Jan village area) as EPC

Employer: General Department of Roads and Transportation of East Azerbaijan Province

Location: East Azerbaijan Province

Design, preparation and implementation of Tabriz-Zanjan axis lighting system (Seyed Beyk village area) as EPC

Employer: General Department of Roads and Transportation of East Azerbaijan Province

Location: East Azerbaijan Province

Optimization, troubleshooting, commissioning, correction and preparation of plans such as construction of reinsurance building

Project location: Tehran – Zayandehrud Street, North Shiraz

Total work area: 2200 meters

Year of implementation: 2016

Improvement of 570 kW diesel generator system equipment

Project location: Refueling Mehrabad Airlines

Total work area: 85 meters

Year of implementation: 2014

Design, supply of goods and complete implementation of electrical installations of Shian Commercial Office Complex

Project location: Tehran – Shian Recreational Residential Complex of the Shipping Company of the Islamic Republic of Iran

Total work area: 12,000 meters

Year of implementation: 2014

Design, supervision and implementation of Mr. Gholami residential complex

Project location: Tehranpars

Total work area: 1200 meters

Year of implementation: 2013

Design and supervision of phase 1 of Ansar Al-Ghadir Hospital

Project location: Roodehen city

Total work area: 6000 meters

Year of implementation: 2013

Design, supervision and implementation of Mr. Seyed Karimi construction complex

Project location: Darous Street

Total work area: 3800 meters

Year of implementation: 1391

Design and supervision of Sona Teb Pharmaceutical Factory

Project location: Mamuniyeh Industrial Town

Total work area: 4500 meters

Year of implementation: 1390

Design and supervision of Parto Maneh Turbine Company

Project location: Karaj

Total work area: 2800 meters

Year of implementation: 2007

Design of Sajafi commercial port site

Project location: Sajafi commercial port

Total work area: 25 hectares

Year of implementation: 2006

Erfan office complex 7000 meters located in Abbasabad

Employer: Life Sazeh Company – Saeed Jaberi

Ajodania Residential Garden Tower 12000 meters located in Ajodania

Employer: Mohammad Abkar

Mobasher Residential Building 10,000 meters located in Elahieh

Employer: Mohammad Malek Sabet

Taban 7000 m office complex located in Mirdamad – South Oil

Employer: Mohammad Malek Sabet

Elahieh residential building 16,000 meters located in Fereshteh – Aghabzorgi

Employer: Mohammad Malek Sabet

Heravi Diamond Commercial-Entertainment-Office Complex 17,000 meters located in Pasdaran

Employer: Karimzadeh Brothers

Versailles dealership 3,000 meters furniture and clothing exhibition complex located in Zafaranieh

Employer: Ali Ansari

Ayandeh Bank Central Building – 33 floors located in Vanak Square – Jahan Koodak intersection

Employer: Ali Ansari

Jamaran Residential Garden Tower 15,000 meters located in Jamaran

Employer: Ali Iraqi

Imam Reza Grand Bazaar 50,000 meters spare parts stock exchange located in Chahardangeh

Employer: Ali Iraqi

Beyhaqi Sports and Medical Complex located in Argentina Square – Beyhaqi

Employer: Mohammad Isfahani and Bank Saderat Partnership

Circulation commercial complex 2 Shahr-e-Bazi – located in Madani

Employer: Haj Agha Moslehi

Design, supervision and implementation of more than 10 projects in the New Thought Design Company

Design and supervision of more than 15 projects in Asa Engineering Company

Feasibility study for preparing and installing a solar power plant in Abbas Abad Industrial Town

Client: Tehran Industrial Towns Company

Year of work: 1400

Feasibility study for preparing and installing a solar power plant in the residential complex of Sina Hotel

Client: Sina Hotel

Year of work: 1400

Feasibility study for preparing and installing a wind power plant in Baran recreational office complex

Client: Golshahr Sepehr Azadegan Company

Year of work: 1399

Feasibility study for preparing and installing a solar power plant in Anarak residential complex

Client: Pardis Fanavaran Company

Year of work: 1399

Haji Baba village lighting construction project in Hormozgan province

Construction of children’s playground lighting in Sarzeh village in Hormozgan province

Construction of solar heating system by solar cell in Chah Tar village of Hormozgan province

Construction of solar heating system by solar cell in Dalakuh village of South Khorasan province

Construction of lighting by solar cell in Azbeco village of South Khorasan province

Construction of solar heating system by solar cell in Neyzar village of South Khorasan province

Our employers

We are proud of the trust of our employers

CONTACT US

Please fill out the relevant form, our experts will contact you as soon as possible.

    FIRST NAME *
    LAST NAME *
    EMAIL ADDRESS *
    PHONE NUMBER

    SUBJECT

    HOW CAN WE HELP?